Capita Symonds Website - A249, Isle of Sheppey
 
Skip Links
 

Find a project:

A249, Isle of Sheppey

The facts

Client:   Carillion
Location:  Isle of Sheppey, Kent
Services:  Highways Design, Geotechnical Design, Environmental Assessment
Sector:   Highways
Contract Type:  HA DBFO
Project Value:  £100m
Start/Completion: 2004 - 2006

The project

A wide range of geotechnical challenges were overcome during the improvement and new construction works for this 30-year Highways Agency DBFO project.

The geotechnical design involved piling, basal reinforced embankments, piled platforms, ground improvement, reinforced soil slopes and temporary working platforms to enable construction and launch of the bridge super structure from either side of the estuary.

Capita Symonds worked intensively with Carillion during the tender stage to put forward a unique series of design solutions for the proposed upgrade works. A fundamental reason for the success of the tender bid was its short construction period. The geotechnical design solutions we proposed were a major contributory factor in ensuring the overall program could be met.

The main geotechnical challenge was that the existing A249 route, originally built on low embankments, required to be widened either side as it crossed extensive flood plains mainly to the north of the new river crossing. The flood plains typically comprised a desiccated crust some 0.75 to 1.2m thick overlying a soft, silty alluvium to depths of up to 11m. Below the alluvium there was up to 2m of dense sand and gravels in turn overlying London Clay.

An additional geotechnical requirement was the design of the two large caisson foundations which would form the central supports for the new bridge crossing. The central shipping channel required that a 24m clear span be formed and demanded that the foundations be designed to allow for a ship impact.

Rather than opt for a piled embankment solution for the areas requiring widening it was determined that the use of band drains and surcharging would achieve the necessary long term settlement characteristics demanded during the 30-year maintenance period. In addition to the band drains, basal reinforcement in the form of a high strength woven geotextile was used under the highest slopes to control lateral sliding and bearing / extrusion failure during the consolidation process. Embankments from 2.5m up to 6m in height had this ground improvement approach used, in conjunction with instrumentation and monitoring.

The instrumentation under these surcharged areas of embankment comprised, inclinometers at the toe of the embankments, piezometers within the alluvium to monitor the rise and dissipation of the excess pore water pressures caused by the surcharging operation. Surface monitoring points were used to verify when the majority of the anticipated settlement had occurred.

Where the embankment was greater than 2.5m high on the approaches to the new bridge the design proposal was for a piled embankment with a geosynthetic reinforced Basal Reinforced Platform (BRP) to transfer the embankment loads to the piles. The embankments were formed from locally sourced London Clay, a Class 2 material. The embankment side slopes were formed at 45 degrees and therefore had to be reinforced due to the inherent weakness of the cohesive fill materials being used. The piles under the embankment were Vibro Concrete Columns (VCC), founded at 16 to 23m depth in the London Clay layer. 900mm diameter bored piles were used under the bridge abutments and went to depths of 25m founding in the dense sand and gravels of the Lambeth beds.

Another major design element for the project was the need for a temporary working platform on the northern side of the estuary to enable not only the construction of the bridge foundations and piers, but also the fabrication and launch of the steel bridge deck structure.

The areas where the working platform was required extended over the tidal mud flats and boggy grassland either side of the existing flood bund. The initial contractor designs for this element of the works indicated an un-reinforced depth of granular material some 1.5 to 3m thick, depending on the prevailing ground conditions; the mud flats had a design strength of some 10 to 15Kpa. A revised design was developed which utilised a composite design technique including high strength woven geotextile reinforcement and lower strength bi-axial geogrids. This design when coupled with edge set backs, and no-go zones for certain plant, ensured that a stable and secure working platform was produced.

Bookmark and Share